New construction / Altadena, CAUnder construction

Las Flores Drive

A ground-up Altadena rebuild on a lot where the previous home was lost to the Eaton Fire — main home and ADU under construction now, documented day by day from the first sheet of floor sheathing.

Location
Altadena, CA
Spaces
Main home, ADU
The arched entry taking shape - windows in, roof on

The build story

The home that stood on this Las Flores Drive lot was lost to the Eaton Fire. When the family decided to rebuild, the plan grew: not just the home they had, but a two-story custom home with a new garage and an ADU above it — second-floor living that adds space the original property never had.

We sequenced the build ADU-first. The ADU's floor sheathing went down on day one, and its structure was finished while the main home's first floor was still being framed — so the smaller building leads the way and the family gets usable space back sooner.

The pace is documented photo by photo below: floor sheathing on day 1, wall framing by day 12, the second-story volume sheathed by day 16. Since then the concrete tile roof has gone on, the arched windows and great-room window wall are in, and the crew has set the multi-panel sliding door. Drive past and you'll see the PMK sign out front.

The build, by the numbers

Project type
Ground-up fire rebuild
Main home
Two-story custom home
Second unit
Garage + ADU with second-floor living
Permit path
L.A. County One-Stop, like-for-like
Status
Under construction

Project gallery

The build so far, documented on site.

Photographed as the work happens - every caption states the actual construction stage, never finished proof. Our jobsites are open, too: prospective clients tour the work in person to judge the quality up close.

The lot before the rebuild, the previous home lost to fire
Day 1 - ADU floor sheathing over the new foundation
Day 12, wall framing, ADU and main home
First-floor framing complete, seen from the street
Day 16, sheathing and the second-story volume
Main home and ADU, framed and sheathed
PMK signage up as framing tops out
Roof underlayment going on
Roof framed, rafter-tail eaves exposed
Roofing day - tile loaded across all three roof planes
Windows in, exterior wrapped
The arched window in
The great-room window wall
Setting the multi-slide door
Exposed ceiling beams inside
The crew on site

Rebuilding in Altadena

Rebuilding after the Eaton Fire? Here is how the process works.

Like-for-like rules, County One-Stop permits, honest itemized pricing, and the homes we are building in Altadena right now.

Altadena rebuild guide
CSLB #1008209 Licensed★ 5.0 on GoogleFounded 2015, 300+ projectsGreater L.A. + O.C.

From blueprint to built reality, starting with a conversation.

Tell us what you're planning. Two minutes, no pressure.